South pars phase13; contaminated amine treated by vacuum distillation
ASSALUYEH –for the first time in oil industry and with high capacity in country, south pars contaminated amine were successfully purified throughvacuum distillation. Director o...More
Date: Sunday, October 21, 2018      
SP13, 22-24; two floodcontrol dams constructed
Referring to heavy rains in south pars region, head of support plans announced that the operation to construct two dams were completed in the upstream of the phases 13, 22-24. Consi...More
Date: Saturday, October 20, 2018      
SP22-24 meets 91 percent progress
ASSALUYEH – while announcing 91 percent progress made in both offshore and onshore sector of the phases 22-24, the director of this plan also added that one billion cubic feet of ...More
Date: Saturday, October 20, 2018      
SP9-10: tip flares successfully replaced
ASSALUYEH – in an intensive operation and under the precise control of Iranian engineers, high and low-pressure tip flares were successfully replaced in two productive platforms b...More
Date: Saturday, October 20, 2018      
SP mega-projects strengthened POGC's position
Assaluyeh - National Iranian Oil Company's deputy in development and engineering affairs stated that pars oil and gas company (POGC) has been able to strengthen its own position by impl...More
Date: Sunday, September 30, 2018      
SP13; 3rd sweetening train to be operational
ASSALUYEH – The 3rd sweetening train will be operational in a few days, managing director announced. As scheduled, the last sweetening train of the phase 13 will be also operat...More
Date: Friday, September 28, 2018      
South pars phase 13; 2 decks loaded out at a time
ASSALUEYEH - Loadout operations were carried out for main and satellite decks in south pars phase 13 development plan. Phase 13' director, Payyam Motamed, announced that SPD-13B (mai...More
Date: Friday, September 28, 2018      
South pars phase13: marine pipelaying operations for second line finalized
ASSALUYEH – marine pipelaying operations for the second main line ended in phase 13, the director of this development plan announced. Having completed the first main and satell...More
Date: Saturday, September 22, 2018      
Page 1 of 91First   Previous   [1]  2  3  4  5  6  7  8  9  10  Next   Last   
Contact Us
Address: No.1 , Parvin Etesami Ave., Fatemi St.
Tel : +98 (21) 88966031-40
 Email : info@pogc.ir
P.O.Box : 1414713111
Fax : +98 (21) 88989273