SP13 first deck installed
ASSALUYEH – the first deck of phase13, weighing 2200 tons, was installed in its location.

Phase13 director, Payyam Motamed, announced two decks called 13B and 13D were simultaneously loaded at SADRA yard to install on their locations last month. The installation was not carried out due to unstable atmospheric conditions. Based on weather forecast report, the operation was performed for the deck 13B last week, public relations reported.
Sailed by the vessel FLB124, this structure was lifted and placed on the jacket by the crane vessel HL5000 and with the attempt of both contractor and employer teams of engineers and experts.
Referring to the daily production capacity of 500 million cubic feet by this platform, Motamed said this platform will be operated on January as Hook-up operation and other activities related to connection are performed.
In case of favorable weather conditions, the second deck called 13D, which had been already loaded and sailed to the sea, will be installed on its jacket in few days.
As these two platforms operated, phase13 enjoys one billion cubic feet of sour gas a day.