South pars phase13; second deck installed
ASSALUYEH – the second deck, 13D, belonging to phase13 was successfully installed in a week after the first deck called 13B.

Simultaneously sailed out from the industrial yard of SADRA, the decks 13D, a week after 13B, was installed today as soon as the weather conditions became stable, PayyamMotamed was quoted by public relations as sayings.
Having started up by the end of January 20, the platforms 13B and 13D will generate 1 billion cubic feet of sour gas, equivalent to 28 million cubic meters, from south pars gas field.
The produced gas from these two platforms is transferred to onshore refinery by two 32-inch pipelines. After processing, some products such as propane, butane, gas condensate as well as sulfur-containing side products are obtained which play a significant role in country's economy.
Phase13 has 38 wells which have been located in northwest of the common field. By operating these two platforms, half of developmental commitment will be fulfilled for the mentioned phase.
Indicated a favorable trend in developmental stages, Motamed announced that phase13 has made 89.5, 95, 94.8, and 89 percent progress in constructing offshore equipment, onshore refinery, laying seabed pipelines, and drilling respectively.In sum, almost 93 percent progress has been made in this development plan.
Phase13 has put 3 sweetening trains into operation since the beginning of spring 2018.So far, these trains have received their feed from the phases 6-7-8 which provide sweetening gas needed for household and industrial consumptions.