SP13; marine pipelaying operation completed
The deputy of marine pipeline project for phase13, Mohsen Azizi, announced that the infield pipelaying operations were completely carried out from the platform 13C to 13A, public relations reported.

Observing all environmental and operational guideline, the 6-kilometer pipelaying operations started on January 24th in difficult condition of the sea and lasted 9 days.

Having performed this part, the entire package of phase13's pipeline was completed at an approximate length of 200 kilometers. Phase13's pipeline is utilized to transfer 56 MCM from offshore to onshore refinery a day, azizi said.

Phase13 has been designed to produce 56 million cubic meters of rich gas, 75000 barrels of gas condensate, 400 tons of sulfur a day as well as 1,100,000 tons of liquid gas, and 1 million tons of ethane a year.\

Contact Us
Address: No.1 , Parvin Etesami Ave., Fatemi St.
Tel : +98 (21) 88966031-40
 Email : info@pogc.ir
P.O.Box : 1414713111
Fax : +98 (21) 88989273