Date: Monday, October 28, 2019
First harbor's loading arms installed in Tombak port
KANGAN – director of service-export port of tombak, PayyamMotamed, announced that three arms for loading propane and butane were installed for the first harbor of the service-export port.

PayyamMotamed said loading and installation operations were carried out with the observance of safety rules and procedures. He added these loading arms include the butane arm, propane, and a common arm, each with a load capacity of 2500 tons per hour.

The director stated that the total progress made in the construction of this plan is 75 percent and expressed hope that the first LPG's shipment will be exported from this port by the end of the current Iranian year (March 20,2019).

According to Motamed, Tombak port aims to export LPG and sulfur produced by phases 13, 14, 19, 22-24 in the region of Tombak (some 200 kilometers away from the capital city of Bushehr). To do that, it is being constructed a sulfur harbor and two LPG harbors which have the possibility to land ships with a capacity of 5 to 50 tons.

Contact Us
Address: No.1 , Parvin Etesami Ave., Fatemi St.
Tel : +98 (21) 88966031-40
 Email : info@pogc.ir
P.O.Box : 1414713111
Fax : +98 (21) 88989273