SP22-24: 3rd deck installed
Assaluyeh – the third deck of phases 22-24 was successfully installed in its location.

As public relations department of Pars Oil and Gas Company (POGC) reported, the 3rd deck of the phases 22-24 weighing 2500 tons was installed on Tuesday (November 12) by the installer vessel called HL5000.

Deputy director of phases 22-24, Ali Asghar Sadeghi, said this deck which belongs to phase 23 is the 2nd main platform of the project. It has the capacity to produce 500mcf of sour gas a day and will be put into operations as soon as hookup and commissioning operations are carried out.

The platform has made 99.22, 70, and 45 percent of progress in construction, pre-commissioning, commissioning stages respectively. There have also been carried out 34000-inch diameter plumbing and over 90km of cabling in the structure of the platform so far.

Sadeghi continued that deck 23 along with its satellite deck, namely 24B, were constructed in Sadra yard of Bushehr. They were simultaneously loaded and sailed to their locations by the carrier vessel called FLB124 on October.