Latest News
Date: Monday, February 10, 2020
SP13; last two decks loaded out simultaneously at SADRA
BUSHEHR - The operation to load out two decks of phase 13 ended at SADRA today February 9. 

The two decks, each weighing about 2500 tons, have made 98 percent progress which were simultaneously loaded on the carrier vessel called FLB124 at manufacturing yard of Iran marine industrial company with the method of Push Pull, director of phase 13, Payyam Motamed, was quoted by public relations as saying.  

He described the operation as one of the most important steps taken to complete the second chain of offshore facility. Following seafastening and offloading works on the carrier vessel, they will be carried to their locations if the weather is favorable. They are then lifted and placed on their jacket by crane vessel HL5000.

According to Motamed, each deck contains 67000 meters of electrical cabling as well as 36000 dia-inch of piping fabrication and has the capacity to extract 500 million cubic feet of sour gas per day.

Phase13 has been designed to produce 56 million cubic meters of rich gas, 75000 barrels of gas condensate, 400 tons of sulfur a day in addition to 1,100,000 tons of liquid gas, and 1 million tons of ethane a year.